Fennovoima and Lehto clinched the contract for the office buildings

Press release
27 June, 2019
Fennovoima and Lehto Group
 


Fennovoima and Lehto Tilat Oy (subsidiary of Lehto Group) have signed an agreement for the design and implementation of the Hanhikivi 1 nuclear power plant’s administration building and plant office. Contract, the value of which is approximately EUR 30 million, is based on the preliminary agreement which was signed in 2018. This is the most significant individual contract under Fennovoima’s scope of works. 

“We are very satisfied with an active and customer-based attitude of Lehto and their designers during the development stage of the project. Together with Lehto we have developed the design solutions of the office buildings during last year and now, with the agreement, we can start to prepare for the construction works”, says Juha Nurmi, director of Fennovoima.

“The final solutions for this project are based on Fennovoima’s original plans, which have been refined with Lehto’s economically-driven construction solutions. The development work has been carried out in close cooperation and we have achieved significant cost-benefits. Fennovoima demonstrated its true spirit of renewal by adopting this type of model for designing and building”, says Jaakko Heikkilä, EVP, Business Premises Service Area at Lehto Group.

The final construction schedule will be specified later during 2019, after the locations of the different parts of the power plant within the plant area have been confirmed. Construction will take approximately year and a half. The target is that both buildings will be fully completed before the construction of the nuclear power plant will begin. Products from Lehto’s Finnish factories, such as wall elements, will be utilized during the construction phase.

The six-storey administration building and plant office will be located within the plant area at Hanhikivi headland. The administration building and the plant office have a combined total space of about 18,000 m2. The administration building will function as Fennovoima’s office building during the power plant’s construction and operation phases. The plant office will have work spaces for the power plant’s operational personnel: for operators, maintenance workers, and technical personnel. During the power plant construction phase, the plant office will also function as Fennovoima’s site office.

Currently, Fennovoima employs nearly 400 people, 50 of them are located in Pyhäjoki. After the completion of the office buildings, the company’s operations will gradually move to Pyhäjoki.

Additional information

Juha Nurmi
Director, Owner Scope Project Area Fennovoima                  
tel. +358 20 757 9214

Mihail Tchitcherin
Communications Officer, Fennovoima
tel. +358 20 757 8452

Share on Facebook
Share on LinkedIn
Share on Twitter